A Bench of Judicial Member Justice N Seshasayee and Technical Member Jatindranath Swain of the NCLAT drew a line between IPCL’s power supply operations and its separate commercial ventures.
It held that the guarantee is enforceable only toward IPCL’s separate business and income from it.
“Both the Electricity Act and the Code operate in different and distinct spheres, and there is hardly any conflict in their working,” the Bench noted.
The NCLAT also faulted both sides for trying to work around electricity rules through contract wording.
“In essence, both the parties were overdriven by commercial ambitions to pursue, and got into a contractual relationship through a consciously contrived drafting (of the agreement) to hoodwink the…