A recent decision by Justice Beech of the Western
Australian Supreme Court in Hamersley Iron Pty Ltd v James
[2015] WASC 101 has considered the issue of whether an
adjudication determination made under the Construction Contracts
Act 2004 (WA) (the Construction Contracts Act) can be enforced by
an insolvent company.
SUMMARY
A court hearing an application by a successful party (made under
section 43 of the Construction Contracts Act) for leave to enforce
a determination will have good reason to refuse leave when:
- the successful adjudication applicant is insolvent, and in
liquidation, at the time that it applies for adjudication of the
relevant payment dispute; and - an adjudication respondent is able to establish that it has…